EPA 2022 Construction General Permit (CGP)
For construction sites disturbing 1 acre or more (or part of a larger common plan of development) where EPA is the permitting authority, including New Hampshire, Massachusetts, New Mexico, the District of Columbia, Puerto Rico, Indian country and certain federal facilities.
- NOI filing fee
- $0 — filed through EPA's NPDES eReporting Tool (NeT)
- Wait before digging
- 14 calendar days after EPA receives a complete NOI
- Inspection schedule
- Every 7 calendar days, or every 14 days plus within 24 hours of a 0.25-inch storm
- Impaired or Tier 2+ waters
- Inspections locked to every 7 days plus the 0.25-inch storm trigger (Table 47)
- Arid / semi-arid ZIP codes
- Seasonally dry period months filled in automatically (Table 32)
The binder follows EPA's own 2022 CGP SWPPP template section for section. Fees and timelines are summarized for planning; confirm current figures with the permitting authority.
$299 per site, paid only after your binder passes the readiness check.